Construction Management and Procurement - sample questions with answers
-
1. During which stages is the technical audit of a project conducted?
Show answer
Answer: Implementation and post-implementation stages
Technical audits of a project are conducted during the implementation and post-implementation stages.
-
2. What is the process of testing whether a decision or action is against the law called?
Show answer
Answer: Ethical filter
An ethical filter tests whether an action or decision is against the law.
-
3. What is the full form of PERT in project management?
Show answer
Answer: Programme Evaluation and Review Technique
PERT stands for Programme Evaluation and Review Technique.
-
4. On what is the Critical Path Method (CPM) network based?
Show answer
Answer: Activity
CPM network is activity oriented, whereas PERT network is event oriented.
-
5. According to the Public Procurement Act 2063, price adjustments are permitted for contracts with a duration exceeding how many months?
Show answer
Answer: 15 months
Under the Public Procurement Act 2063, price adjustments are permitted for contracts with a duration exceeding 15 months.
-
6. The Nepal Engineering Council (NEC) is an autonomous body established under which Act?
Show answer
Answer: NEC Act 2055
The Nepal Engineering Council is an autonomous body established under the NEC Act of 2055.
-
7. When was the Nepal Engineer's Association established?
Show answer
Answer: 2024 BS
The Nepal Engineer's Association was established in 2024 BS.
-
8. Which two processes are involved in quality control?
Show answer
Answer: Detection and Prevention
Quality control involves both detection and prevention.
-
9. Which of the following procurement methods is not applicable for material management?
Show answer
Answer: Cost and quality-based selection
Cost and quality-based selection is not a procurement method applicable for material management.
-
10. What is the total float of activities on the critical path?
Show answer
Answer: Zero
Activities on the critical path have a total float of zero.
-
11. What is the person designated within a construction contract for the resolution of disputes called?
Show answer
Answer: Contract Adjudicator
A contract adjudicator is a person designated within the contract for the resolution of disputes.
-
12. According to engineering ethics, which action is considered unethical?
Show answer
Answer: Reviewing another engineer's work without consent
Reviewing the work of another engineer without their consent is considered unethical.
-
13. Which document is used to record wages in construction management?
Show answer
Answer: Muster roll
In construction management, a muster roll is used to record wages.
-
14. What is meant by 'Crashing' in project management?
Show answer
Answer: Reduction of project duration
Crashing refers to the reduction of project duration.
-
15. What is the full form of CPM used in project management?
Show answer
Answer: Critical Path Method
CPM stands for Critical Path Method.
This chapter has 113 questions. Practise them all with timing, answers and explanations.