Estimating, Costing and Valuation

132 questions

Sign in to use this feature.

Read mode

Estimating, Costing and Valuation - sample questions with answers

  1. 1. What are the documents containing detailed descriptions of work items and their current rates without quantities called?

    Show answer

    Answer: Schedule rates

    Schedule rates are documents containing detailed descriptions of work items and their current rates without quantities.

  2. 2. Overheads are considered as which type of cost in construction work?

    Show answer

    Answer: Indirect cost

    Overheads are considered an indirect cost in construction work.

  3. 3. Which method is used for estimating circular, hexagonal, and other geometrically shaped buildings?

    Show answer

    Answer: Center line method

    The center line method is used for estimating circular, hexagonal, and other geometrically shaped buildings.

  4. 4. Which of the following is included in a project construction cost estimate?

    Show answer

    Answer: Labor, material, equipment, overhead costs, and contractor's profit

    A project construction cost estimate includes labor, material, equipment, overhead costs, and the contractor's profit.

  5. 5. What is the volume of one bag of cement?

    Show answer

    Answer: 0.033 m³

    The volume of cement in one bag is 0.033 m³.

  6. 6. What are the annual periodic payments made to repay invested capital termed?

    Show answer

    Answer: Annuity

    Annual periodic payments made to repay invested capital are termed an annuity.

  7. 7. What is the normal scrap value of wood used six times in formwork for rate analysis?

    Show answer

    Answer: 10%

    The scrap value of wood used six times in formwork for rate analysis is normally 10%.

  8. 8. What represents the probable cost of a project?

    Show answer

    Answer: Estimate

    An estimate represents the probable cost of a project.

  9. 9. What is the annual periodic payment used to repay a capital investment over a fixed period called?

    Show answer

    Answer: Annuity certain

    An annuity certain is an annual periodic payment used to repay a capital investment over a fixed period.

  10. 10. For openings of what maximum area is no deduction made in masonry estimation?

    Show answer

    Answer: 0.1 m²

    No deduction is made in masonry for openings with an area not exceeding 0.1 m².

  11. 11. Which method is adopted while measuring the dimensions of a door or window frame?

    Show answer

    Answer: Outer to outer on the vertical side and inner on the other side

    Door or window frame dimensions are measured outer to outer on the vertical side and inner on the other side.

  12. 12. What is the amount provided in an estimate for specialized works by a firm whose details are unknown during estimate preparation called?

    Show answer

    Answer: Provisional sum

    A provisional sum is the amount provided in an estimate for specialized works by a firm whose details are unknown during estimate preparation.

  13. 13. The 'Time Value' of money refers to the relationship between time and what?

    Show answer

    Answer: Interest

    The time value of money is the relationship between time and interest.

  14. 14. What is the primary purpose of rate analysis?

    Show answer

    Answer: To determine the actual cost per unit item

    The primary purpose of rate analysis is to determine the actual cost per unit item.

  15. 15. Which of the following are included in the service area of a building?

    Show answer

    Answer: Toilets, stairs, lights, and shafts

    The service area of a building includes utility zones such as toilets, stairs, lights, and shafts.

This chapter has 132 questions. Practise them all with timing, answers and explanations.